News Register

Australian major energy projects

A simple weekly-updated list of major projects that are planned, in approvals, procurement, construction or commissioning.

Weekly news Panel participants Last updated from Australian energy sector news – week ending 13 September 2026
Project State Owner / proponent Voltage / overhead scope Stage Latest development Delivery parties Target date Sources
Central‑West Orana REZ Transmission NSW EnergyCo NSW (licensing to network operator)
EnergyCo NSW
500 kV (backbone) with 330 kV connections (per EPBC referral)
New twin double‑circuit 500 kV backbone; single/double‑circuit 330 kV lines to energy hubs; new switching stations and hubs.
Not stated in a single total – multiple sections
construction Offset delivery progress report (Apr–Jun 2026) published 11 Sep 2026; construction program continues toward energisation in 2028.
New quarterly offset report published within the week.
Verified: 13 Sep 2026
ACEREZ consortium appointed as network operator (design/finance/operate/maintain) – previously announced Initial energisation 2028 (program statements) EnergyCo – project page
EPBC referral (scope/voltages)
Offset progress report Apr–Jun 2026
HumeLink NSW Transgrid
Transgrid
500 kV
New dual‑circuit 500 kV overhead transmission linking Wagga Wagga, Bannaby and Maragle; West section delivered by UGL‑CPB JV; East by Acciona–Genus JV.
~365 km (publicly stated)
construction Late‑August 2026 construction notices issued for multiple localities; West section stringing ongoing; no new schedule published this week.
Added Aug‑week construction notices; no schedule change verified.
Verified: 30 Aug 2026
UGL–CPB Contractors JV (West), Acciona–Genus JV (East) Not publicly restated as at Aug 2026 HumeLink West – project page (Aug 2026 notices; West scope)
HumeLink towers fact sheet (scope and ~365 km length)
Genus – HumeLink project JV scope (East)
HumeLink NSW Transgrid
Transgrid
500 kV
New double‑circuit 500 kV overhead lines linking Wagga Wagga, Bannaby and Maragle, with associated new/upgraded substations.
≈365 km
construction August 2026 construction notices issued for multiple localities; ongoing tower assembly/stringing on HumeLink West; no scope changes confirmed this week.
Status unchanged this week; works continuing across both packages.
Verified: 30 Aug 2026
UGL, CPB Contractors, ACCIONA, GenusPlus Group Q4 2027 (per Transgrid 2025 disclosure, subject to revision) HumeLink overview
HumeLink West – Aug 2026 works
HumeLink project update (delivery partners)
HumeLink NSW Transgrid
Transgrid
500 kV
New 500 kV overhead double‑circuit lines linking Wagga Wagga, Bannaby and Maragle; associated new/upgraded substations.
~365 km (East ~225 km; West ~140 km)
construction Main construction is in progress on East and West packages; tower erection and substation builds underway.
Construction status reconfirmed; no new scope changes published this week.
Verified: 13 Sep 2026
Acciona–GenusPlus JV (HumeLink East), UGL–CPB JV (HumeLink West) Construction finish proposed 2027 (Transgrid timeline) HumeLink overview
HumeLink East
HumeLink West
HumeLink (East and West) NSW Transgrid
Transgrid
500 kV AC (dual circuit)
Approximately 365 km of new 500 kV double‑circuit overhead lines connecting Wagga Wagga, Maragle and Bannaby, plus new/expanded 500 kV substations.
~365 km
construction 3 Sep newsletter reports >100 towers erected on HumeLink West; conductor stringing underway; transformer/reactor deliveries completed at Maragle; 2 Sep HumeLink West Biodiversity Management Plan Rev 7 posted.
Construction progress and updated management plans published during the week.
Verified: 06 Sep 2026
Acciona/Genus JV (HumeLink East), UGL/CPB Contractors JV (HumeLink West) 2027-12 (AEMO ISP in‑service) HumeLink West — Sep 2026 newsletter
HumeLink West — documents (BMP Rev 7)
HumeLink length/scope factsheet
AEMO 2026 ISP (timing)
Hunter Transmission Project NSW EnergyCo NSW (Transgrid as preferred network operator)
EnergyCo NSW
500 kV
New ~110 km overhead 500 kV line Bayswater–Olney with new switching stations; corridor predominantly through mining/energy/government land.
~110 km (project material)
procurement September 2026 work notifications for surveys and investigations; detailed design and tender process underway following July approval.
Work notifications posted for September; no contract award yet.
Verified: 13 Sep 2026
- Construction expected late 2026–late 2029 (subject to remaining requirements) HTP – main page
HTP – project resources
Hunter Transmission Project (HTP) NSW EnergyCo NSW (planning); Transgrid (preferred network operator)
EnergyCo NSW
500 kV
~110 km new 500 kV overhead line between Bayswater and Olney; creation of the NSW 500 kV ring.
~110 km
procurement Planning approval issued July 2026; August 2026 field work notifications commenced; shortlists in place for line and substations packages.
Status shifted to procurement following July approval; August field notices noted.
Verified: 30 Aug 2026
Preferred network operator: Transgrid (commitment deed), Shortlisted D&C tenderers as per EnergyCo release Construction start late 2026; completion targeted 2029 (per EnergyCo FAQ) HTP main page (approval and 500 kV scope)
HTP resources (Aug/Sep 2026 notices)
HTP industry – shortlists and procurement
Hunter Transmission Project (Sydney Ring North) NSW EnergyCo (NSW)
EnergyCo (NSW)
500 kV AC (double circuit)
~110 km new 500 kV overhead double‑circuit line between Bayswater and Olney.
~110 km
approvals Planning approval granted in July 2026; services procurement advance notice issued mid‑August for release early September.
No new approvals this week; upcoming services tender flagged.
Verified: 06 Sep 2026
- 2029-11 (AEMO ISP in‑service) HTP project page (approval and scope)
Advance notice — HTP technical & construction support services
AEMO 2026 ISP (timing)
Mount Piper to Wallerawang Transmission Line Upgrade NSW Transgrid
Transgrid
Unconfirmed on project page
Upgrade works between Mount Piper and Wallerawang with associated substation interfaces.
Not stated
construction Pre‑construction in July 2026; construction works proposed for September 2026 per project timeline.
No new notices beyond the posted month‑level schedule.
Verified: 13 Sep 2026
- Commissioning proposed November 2026 Project page
New England REZ – Network Infrastructure Project NSW EnergyCo NSW
EnergyCo NSW
500 kV backbone and 330 kV connections (proposed)
Proposed dual 500 kV circuits between Bayswater and New England REZ, plus 500/330 kV internal REZ links to hubs.
~305 km (indicative)
approvals 28 Aug 2026 program page update (no change to transmission scope). EIS exhibition planned for H2 2026.
No change to scope; recorded page update and exhibition timing.
Verified: 30 Aug 2026
- Not publicly stated New England REZ network infrastructure
CEB Program page (updated 28 Aug 2026)
Sydney Ring – South (RIT‑T PADR) NSW Transgrid
Transgrid
Unconfirmed (RIT‑T stage)
Unconfirmed (RIT‑T investigations may include overhead/underground options).
Unconfirmed
approvals PADR consultation window closed 28 Aug 2026; awaiting submissions summary and next RIT‑T step.
Recorded closure of PADR submissions.
Verified: 30 Aug 2026
- Not publicly stated Sydney Ring – South (RIT‑T PADR)
Project EnergyConnect Stage 2 (NSW–SA) NSW/SA Transgrid (NSW) / ElectraNet (SA)
Transgrid and ElectraNet
330 kV AC (double circuit)
New interconnector between Robertstown (SA) – Buronga – Wagga Wagga (NSW), with augmentation into Victoria.
~900 km total across SA and NSW
commissioning preparations AER published preliminary position on Transgrid’s capex re‑opener (1 Sep 2026); AEMO indicates energisation and inter‑network testing targeted for November 2026.
Regulatory consultation step; no change to testing target date.
Verified: 06 Sep 2026
Transgrid, ElectraNet 2026-11 (start inter‑network testing) AER consultation paper — preliminary position
AEMO — PEC Stage 2 inter‑network test program (draft)
Transgrid — EnergyConnect overview
Project EnergyConnect (NSW section and market integration) NSW/SA/VIC Transgrid (NSW) / ElectraNet (SA) / AusNet (Vic)
Transgrid and ElectraNet
330 kV (overhead sections)
NSW overhead scope built; staged market capacity release subject to AEMO inter‑network testing.
NSW backbone ~700 km per Transgrid reporting (Western section previously completed/energised).
commissioning 26 Aug 2026 Transgrid article: NSW construction completed earlier in 2026; AEMO Stage 2 inter‑network testing program in place to progressively release capacity.
Status clarified as commissioning/integration rather than fully in‑service at full transfer.
Verified: 30 Aug 2026
Transgrid, ElectraNet, AusNet (Vic interface) Staged testing and capacity release through 2026–2027 (per AEMO program context) Transgrid – EnergyConnect social value article (states NSW construction completed earlier in 2026)
AEMO – PEC Stage 2 inter‑network test program
Calvale to Calliope River Transmission Line Reinforcement QLD Powerlink Queensland
Powerlink Queensland
unconfirmed publicly
New transmission line between Calvale and Calliope River substations, plus substation upgrades and a 500 MVA transformer.
≈20 km (portion awarded to CPP; full length unconfirmed)
construction Construction contract awarded to CPP on 31 Aug 2026 for a 20 km section and substation works.
New contract award during the week.
Verified: 30 Aug 2026
Consolidated Power Projects (CPP) unconfirmed CPP contract award – Central Queensland
Calvale–Calliope River
CopperString 2032 QLD QIC‑managed entity (delivery/ownership); Powerlink (transition, Eastern Link early works)
Queensland Government / Powerlink / QIC
500 kV (Townsville–Hughenden); 330 kV (Hughenden–Cloncurry/Mt Isa) per approvals
Approximately 1,000 km of new overhead lines connecting Townsville to Mount Isa with southern spur to Selwyn; staged delivery (Eastern Link early works).
~1,000 km
procurement No new publications this week. Project transition to QIC noted by Queensland Treasury; Eastern Link early works continue under Powerlink.
No verified change this week.
Verified: 06 Sep 2026
UGL/CPB JV noted for earlier works (Powerlink comms) 2032 (commercial operations per Qld Treasury) Coordinator‑General project page (scope/length)
Powerlink — CopperString project page
Queensland Treasury — Transmission (QIC delivery note)
CopperString Eastern Link (Reid River to Hughenden) QLD Queensland Government (delivered via QIC), with Powerlink involvement
Powerlink Queensland / QIC
330 kV
Approx. 330–350 km overhead line from Reid River (near Townsville) to Hughenden; remaining western supply to be supported by regional solutions under the Roadmap.
≈350 km
approvals Queensland Energy Roadmap (Nov 2025) sets Eastern Link completion by 2032, major construction by 2028, with 330 kV scope reaffirmed.
No weekly change.
Verified: 30 Aug 2026
CPB‑UGL JV (early works noted historically) 2032 (commercial operations, subject to approvals) Qld Treasury – Transmission (Energy Roadmap)
EPBC referral summary – Reid River–Hughenden
Project EnergyConnect (PEC) SA/NSW ElectraNet (SA), Transgrid (NSW)
ElectraNet and Transgrid
330 kV
New 330 kV double‑circuit interconnector Robertstown–Buronga–Wagga Wagga, with strengthening towards Red Cliffs (VIC).
≈900 km (combined)
construction AEMO indicates Stage 2 expected to energise and commence inter‑network testing in Nov 2026; PEC market‑integration Industry Q&A released 28 Aug 2026.
No scope change recorded this week; market‑integration materials updated.
Verified: 30 Aug 2026
ElectraNet, Transgrid Inter‑network testing from Nov 2026 (AEMO) PEC Stage 2 inter‑network test program
PEC market integration – Industry Q&A (28 Aug 2026)
Project EnergyConnect (SA–NSW–VIC) SA/NSW/VIC ElectraNet (SA), Transgrid (NSW)
ElectraNet and Transgrid
330 kV (main interconnector)
New 330 kV AC interconnector Robertstown–Buronga–Wagga Wagga with a 220 kV spur to Red Cliffs; staged commissioning/testing.
~900 km (project corridor)
commissioning AEMO’s integration timeline targets dispatch inclusion (1 Oct 2026) and settlements changes (2 Nov 2026) ahead of full capacity release, subject to testing.
Integration dates reconfirmed on AEMO page; AER reopener consultation noted separately.
Verified: 13 Sep 2026
- Q4 2026 (Stage 2 completion / market integration sequencing) Transgrid – EnergyConnect
ElectraNet 2026 TAPR (330 kV confirmation)
AEMO – PEC‑MI
North West Transmission Developments (NWTD) — Stage 1 TAS TasNetworks
TasNetworks
220 kV and 110 kV upgrades/new (overhead)
Stage 1 includes ~3 km new and ~126 km upgraded overhead lines; associated new substations and a switching station between Cressy and Burnie.
~129 km (Stage 1 new + upgraded lines)
construction Notice to proceed issued 31 Aug 2026 to head contractor Genus; construction commenced.
Moved into construction with NTP issued during the week.
Verified: 06 Sep 2026
Genus (head contractor) Construction start 2026-08-31 (Stage 1); in‑service date TBA NWTD construction start — media release
NWTD — Building the project (scope)
North West Transmission Developments (Stage 1) TAS TasNetworks
TasNetworks
Unconfirmed on current page
New/augmented transmission between North‑West and Burnie nodes; staged program linked to Marinus and REZ growth.
Not stated
construction TasNetworks notes notice‑to‑proceed to head contractor Genus and start of construction in August 2026.
Status moved into construction in August; no in‑week change.
Verified: 13 Sep 2026
Genus (Stage 1 head contractor) Staged delivery 2026 onward NWTD project page
Western Renewables Link VIC AusNet Services
AusNet Services
Unconfirmed on current public summary
Proposed new overhead line between Bulgana and Sydenham; EES exhibited in 2025; Ministerial assessment pending.
~190 km (project description)
approvals IAC report lodged 8 May 2026; awaiting Minister’s assessment.
No new Ministerial assessment published this week.
Verified: 13 Sep 2026
- Subject to Minister’s assessment and subsequent approvals. WRL – EES landing
Western Renewables Link (WRL) VIC AusNet (delivery under AEMO contract)
AusNet / AEMO Victorian Planning
500 kV AC (double circuit, with associated 220 kV works)
New ~190 km overhead 500 kV double‑circuit line between Bulgana and Sydenham; ~2.5 km of 220 kV line to a new 500 kV terminal near Bulgana.
~190 km (500 kV)
approvals No new approvals this week; EES process continues in Victoria.
No verified change this week.
Verified: 06 Sep 2026
AusNet (constructor) 2029-11 (AEMO ISP in‑service) WRL — Victorian planning page (scope/length)
WRL — AusNet project overview
Victoria–NSW Interconnector West (VNI West) — Victorian component VIC/NSW AEMO Victorian Planning (VIC) / Transgrid (NSW)
AEMO Victorian Planning and Transgrid
500 kV AC (double circuit)
New 500 kV double‑circuit overhead interconnector linking WRL (Bulgana) to NSW (Kerang/Murray River crossing).
Unconfirmed in Victoria pending EES; corridor scale project.
approvals No new approvals during the week. EES requirement in Victoria remains in place; AEMO material notes delivery commencing 2026 with staged in‑service dates from 2029–2030 per ISP.
No verified change this week.
Verified: 06 Sep 2026
- 2029–2030 (staged per AEMO ISP) VNI West — EES requires assessment (Reasons for Decision)
AEMO 2026 ISP (timing)
VNI West (Victoria to NSW Interconnector West) VIC/NSW Transgrid (NSW), Transmission Company Victoria (VIC)
Transgrid (NSW), TCV/VicGrid (VIC)
500 kV
Proposed 500 kV double‑circuit overhead line connecting Dinawan (NSW) to a new Kerang terminal and Bulgana (VIC).
Not confirmed on a single authoritative source
approvals NSW EIS exhibited Aug 2025; Victorian EES preparation continues with public exhibition expected in 2026.
No new approvals issued this week; status unchanged.
Verified: 13 Sep 2026
- Delivery sequencing aligned to Victorian approvals; NSW staged delivery flagged in July 2025 update. Transgrid – VNI West (NSW)
VNI West NSW EIS summary
VNI West – EES FAQs (VIC)
Clean Energy Link – Northern Terminal to Neerabup 330 kV line WA Western Power
Western Power
330 kV
New double‑circuit 330 kV overhead line Northern Terminal (Malaga) to Neerabup Terminal (Pinjar), ~28 km, plus terminal augmentations within Clean Energy Link – North.
~28 km
approvals Project referral for environmental approval noted by Western Power; project page active; no dated construction start published during the week.
No dated start this week; retained with environmental referral context.
Verified: 30 Aug 2026
Western Power (owner/constructor) Not publicly stated Northern Terminal to Neerabup 330 kV
environmental referral submitted (Malaga–Pinjar 330 kV)
Northern Terminal to Henley Brook Substation line WA Western Power
Western Power
132 kV
New overhead 132 kV line between Northern Terminal and Henley Brook (Clean Energy Link – North).
≈5 km
construction Stage‑three pole‑installation works notice dated 20 Aug 2026; construction continuing.
No weekly change.
Verified: 30 Aug 2026
Acciona (contractor) unconfirmed Western Power – project page (works notice 20 Aug 2026)